SCHEDULE
TYPICAL SCHEDULE / LEAD TIME*
TYPICAL SCHEDULE / LEAD TIME*
WEEK 1: SITE MEASUREMENT + DETAILS
WEEK 1: SITE MEASUREMENT + DETAILS
Site measurement
Finalize details
Confirm finished dimensions
WEEK 2-3: SHOP DRAWINGS
WEEK 2-3: SHOP DRAWINGS
TIW produces initial round of shop drawings
Client provides feedback / redlines of shop drawings
TIW revises and resubmits drawings
Shop drawings approved
WEEK 4: ENGINEERING
WEEK 4: ENGINEERING
Long lead time items are ordered (buy-out doors and drawers)
Project is engineered
WEEK 5-8: FABRICATION
WEEK 5-8: FABRICATION
Parts processing and assembly (1-3 weeks depending on project size)
WEEK 7-10: FINISHING
WEEK 7-10: FINISHING
Finish (only applicable if you've selected a paint grade or stain grade finish)
WEEK 8-13: INSTALLATION
WEEK 8-13: INSTALLATION
Installation (1-3 weeks depending on project size)
*THIS CAN VARY WIDELY DEPENDING ON VARIABLES SUCH AS SCOPE, FINISHES, CURRENT WORK LOAD, ETC.