SCHEDULE

TYPICAL SCHEDULE / LEAD TIME*

WEEK 1: SITE MEASUREMENT + DETAILS

      • Site measurement

          • Finalize details

          • Confirm finished dimensions

WEEK 2-3: SHOP DRAWINGS

      • TIW produces initial round of shop drawings

      • Client provides feedback / redlines of shop drawings

      • TIW revises and resubmits drawings

      • Shop drawings approved

WEEK 4: ENGINEERING

      • Long lead time items are ordered (buy-out doors and drawers)

      • Project is engineered

WEEK 5-8: FABRICATION

      • Parts processing and assembly (1-3 weeks depending on project size)

WEEK 7-10: FINISHING

      • Finish (only applicable if you've selected a paint grade or stain grade finish)

WEEK 8-13: INSTALLATION

      • Installation (1-3 weeks depending on project size)

*THIS CAN VARY WIDELY DEPENDING ON VARIABLES SUCH AS SCOPE, FINISHES, CURRENT WORK LOAD, ETC.